  1. Surface Preparation – Clean cracks by removing dust, loose particles, and weak plaster.

  2. Crack Cutting – Open cracks in V-groove shape using a cutter for better bonding.

  3. Cleaning – Wash and dry the groove properly to remove debris.

  4. Filling – Fill cracks with polymer-modified mortar / epoxy / PU sealant as per requirement.

  5. Finishing – Level the surface smooth, cure if cementitious, and check for proper sealing.

  • Facebook
  • Twitter
  • LinkedIn
WhatsApp Image 2025-08-21 at 2.28.45 AM (4).jpeg
  • Facebook
  • Twitter
  • LinkedIn

Comorcial shed

  • Surface Preparation – Clean shed roof/sheets thoroughly, remove rust, dust, algae, and loose coatings.

  • Crack & Joint Treatment – Seal bolt joints, overlaps, and cracks with PU sealant / butyl tape / flashing tape.

  • Primer Application – Apply compatible primer on metal/concrete surface for strong bonding.

  • Waterproof Coating – Apply 2–3 coats of elastomeric/acrylic/polyurethane waterproof coating or bituminous membrane.

  • Final Inspection – Check for uniform coverage, no leak points, and ensure proper curing before handover.

  • Facebook
  • Twitter
  • LinkedIn
WhatsApp Image 2025-08-21 at 2.28.48 AM (2) (1).jpeg

Terace coting

  • Surface Preparation – Clean terrace surface, remove dust, algae, loose plaster, and repair cracks with polymer-modified mortar.

  • Primer Application – Apply waterproof primer coat for proper adhesion.

  • Crack Treatment – Fill cracks/joints with PU sealant or polymer grout.

  • Coating Application – Apply 2–3 coats of elastomeric/acrylic/polyurethane waterproof coating as per manufacturer’s specification.

  • Final Inspection – Check for uniform coverage, ensure no pinholes, and allow proper curing before use.

  • Facebook
  • Twitter
  • LinkedIn
IMG_20250908_151332 (1).jpg

PU injuction grouting

  • Surface Preparation – Identify leakage points, clean surface, and mark drilling spots along cracks/joints.

  • Drilling & Nozzle Fixing – Drill 8–12 mm holes at 300–500 mm spacing and fix injection packers.

  • Mixing of PU Grout – Prepare polyurethane grout as per manufacturer’s ratio (base + catalyst).

  • Injection – Inject grout under controlled pressure until refusal or material flows out from adjacent packers.

  • Finishing & Inspection – Remove packers, seal holes, and check treated area for leakage-proof performance

WhatsApp Image 2025-09-04 at 8.25.11 PM.jpeg

Bathroom Grouting

  • Surface Preparation – Clean tiles, remove old/damaged grout, dust, and loose material.

  • Crack / Joint Marking – Identify hollow tiles, cracks, and joints to be treated.

  • Grout Mixing – Prepare cementitious / epoxy / PU grout as per manufacturer’s instructions.

  • Application – Fill/inject grout into cracks, joints, and voids using pump/float.

  • Finishing & Curing – Wipe excess grout, smoothen joints, and cure (if cement-based

  • Facebook
  • Twitter
  • LinkedIn
  • Facebook
  • Twitter
  • LinkedIn

Plumbimg

  • Site Preparation & Marking – Study drawings, mark pipe routes for water supply, drainage, and sanitary lines.

  • Cutting & Chasing – Cut walls/floors carefully for pipe laying, ensuring minimum damage to structure.

  • Pipe Laying & Fixing – Install pipes (CPVC, UPVC, GI, etc.) with proper slope, clamps, and jointing materials.

  • Testing – Conduct pressure testing for water supply lines and leak testing for drainage lines.

  • Finishing – Seal chases, restore plaster/tiles, and hand over a neat, leak-free system.

  • Facebook
  • Twitter
  • LinkedIn
IMG_20250908_151332.jpg
bottom of page